Project Milestones
January 5, 2015:
Construction and utility work began from Midway Boulevard to West Spring Lake Bridge (Area 1).
January 12, 2015:
Construction will require lane closures and detours
January 2015:
Lauzon Avenue closed to thru traffic for duration of project
March 2, 2015:
Edgewater Drive closed to thru traffic as work began on East Spring Lake Bridge.
March 23, 2015
Work began on West Spring Lake Bridge
July 2015:
Work begins from East Spring Lake Bridge to Sunrise Waterway Bridge (Area 3).
JULY 2015
- Pile driving underway on West Spring Lake Bridge
AUGUST 2015
- New lift station constructed at Altoona St.
- New sanitary sewer underway from Altoona St. to Midway Blvd.
- New water main constructed from Sunrise Bridge to Harbor Blvd.
- New water main and force main installed in Harbor Blvd. intersection
- Completed storm sewer outfall at Lakeview Blvd.
- Pile driving completed on West Spring Lake Bridge
- Old West Spring Lake Bridge demolished
SEPTEMBER 2015
- Sanitary sewer construction continues between Altoona St. and Midway Blvd.
- New storm sewer construction underway between West Spring Lake Bridge and East Spring Lake Bridge
- New reuse water main installed in Harbor Blvd. intersection
- West Spring Lake Bridge substructure construction continues
January 2016:
Work begins from Sunrise Waterway Bridge past Harbor Boulevard (Area 4).
November 2016:
Work begins at Edgewater Drive and Harbor Boulevard Intersection (Area 5).
March 2017:
Scheduled completion.